Skip to the sheet
Tailgate BriefSTSC study sheets
Menu

Sheet 25Mix-up sheet · Falls, ladders and scaffolds

Fall protection trigger heights: 6 feet, not 4

OSHA requires fall protection at 6 feet above a lower level in construction, under 29 CFR 1926.501. The 4-foot figure you will also hear on site belongs to general industry (29 CFR 1910.28). Two construction subparts set their own height on top of that: 10 feet for scaffolds and 15 feet for steel erection.

Where the 4 comes from

Both rule books protect people at an edge and draw the line at different heights. General industry, which covers plants, warehouses and fixed facilities, uses 4 feet. Construction uses 6 feet throughout Subpart M: unprotected sides and edges, leading edges, hoist areas, formwork and rebar, ramps and walkways, excavation edges, wall openings, and both low-slope and steep roofs. When someone quotes 4 feet for a construction edge, they are quoting the neighboring rule book.

The scaffold and steel-erection heights apply only inside Subpart L and Subpart R. Steel erection also lets connectors work up to two stories or 30 feet, whichever is less, before they need a system (29 CFR 1926.760(b)). A worker who steps off the scaffold onto a floor deck is back under the 6-foot rule of Subpart M. Fixed ladders have a 24-foot trigger of their own, covered with the 4-to-1 rule on ladder rules, and the rest of the access topics are on falls, ladders and scaffolds.

Trigger heights on one line

0 ft32 ft4 ftGeneral industry,19106 ftConstruction,Subpart M10 ftScaffolds, Subpart L15 ftSteel erection24 ftFixed ladders30 ftConnectors, or 2stories
Heights above a lower level at which each rule first requires protection. Only the 4 ft mark comes from general industry.

Below 6 feet still has rules

Holes
Protection against falling through applies to holes more than 6 feet above a lower level (29 CFR 1926.501(b)(4)), yet a hole 2 inches or more across needs a cover at any height, against trips, step-ins and dropped tools. Covers carry twice the load placed on them, or twice the heaviest axle load in a roadway.
Dangerous equipment
Above equipment that can injure on contact, such as a mixer or other machinery, a guardrail or equipment guard is required at any height (29 CFR 1926.501(b)(8)).
Overhand bricklaying
A mason who reaches more than 10 inches below the working surface needs a guardrail, a net or a personal fall arrest system; a controlled access zone alone does not cover the reach.
Roof warning lines
On a low-slope roof a warning line stands at least 6 feet back from the edge, and at least 10 feet back on edges perpendicular to the direction mechanical equipment travels.

The hardware numbers that come with the trigger

Subpart M system criteria, 29 CFR 1926.502
ComponentRequirementWorth knowing
Guardrail top rail42 in, plus or minus 3 inA 200 lb test load may not push it below 39 in
MidrailAbout halfway upHolds 150 lb; not needed behind a wall or parapet at least 21 in high
Toeboard3.5 in minimumWithstands 50 lb
Fall arrest anchorage5,000 lb per worker attachedTwo workers on one anchor means 10,000 lb, unless a qualified person designs it with a safety factor of 2
Safety netNo more than 30 ft below the workInspected at least weekly

Who counts as a qualified person, and how that differs from a competent one, is on competent person vs qualified person.

Heights and hardware

Picture the edge, and the people working below it, before you pick an answer.

Card 1 of 6 · 0 right

Card 1

A supervisor finds a loose, unmarked sheet of plywood lying over a 3-foot-square floor hole on an upper deck. What should the supervisor require?

Pick an answer. A short note for each option, A to D, appears here.

Card 2

What is the PRIMARY purpose of the toeboard on a scaffold platform?

Pick an answer. A short note for each option, A to D, appears here.

Card 3

During a rushed deck pour, a supervisor sees a worker remove a hole cover to pass a pump hose through, leaving the opening unprotected. What should the supervisor do FIRST?

Pick an answer. A short note for each option, A to D, appears here.

Card 4

HVAC installers will work for several days within 4 ft of an unprotected edge on a flat roof 20 ft above grade. Which control ranks HIGHEST in the hierarchy of controls?

Pick an answer. A short note for each option, A to D, appears here.

Card 5

An ironworker plans to clip a 6-foot shock-absorbing lanyard to an anchor at the level of the worker's boots, because nothing overhead is available. What is the main problem with this setup?

Pick an answer. A short note for each option, A to D, appears here.

Card 6

A newly hired worker finds that the only harness available on site is too large to adjust snugly. The task requires personal fall arrest. What should the supervisor do?

Pick an answer. A short note for each option, A to D, appears here.

    Next sheets

    Lock in the difference

    Mix-ups stick when you see them again in a day or two. The app keeps them coming.